The Minister of Housing, Urban Planning and the City, Mr. Mohamed Tarek Belaribi insisted on accelerating the pace of work and finalizing the projects within the set deadlines, in order to guarantee the distribution of housing to beneficiaries in the best conditions.

The minister, who chaired a technical meeting dedicated to monitoring the progress of housing projects scheduled for the major distribution operation on July 5, 2024, was able to monitor the progress of each project in the wilayas concerned using of videos. This innovative approach made it possible to obtain a precise and detailed vision of the progress of the work on the different construction sites.

The distribution operation concerns all the wilayas of Ghardaïa, Ouargla, Biskra, Batna, Sétif, Mila, Tébessa, Guelma, Constantine, Jijel, Skikda, Annaba, Oran, Chlef, Mostaganem, Adrar, Sidi Bel Abbès and Relizane.

In the presence of the central executives of his department, the general director of the National Agency for the Improvement and Development of Housing (AADL) as well as the regional directors of Annaba, Oran, Constantine, Sétif and Ouargla, the minister instructed concerned officials to remove all obstacles and make all necessary arrangements to ensure delivery of projects in accordance with the required quality standards.

It should be recalled that Minister Belarbi announced, during a previous intervention, the distribution of 40,000 AADL housing units in the wilaya of Algiers, including 20,000 units in Sidi Abdellah, on the occasion of the 62nd anniversary of independence. .

The minister affirmed that these completed housing units have all the necessary amenities, after his ministerial department took care to reconcile the construction of housing and the construction of public facilities.

He also welcomed the speed of completion of the urban center of 13,300 housing units in Sidi Abdellah, work on which began at the end of 2021.

Mr. Belaribi underlined, in this sense, that the rate of progress of the work of the 10,507 housing project, the kick-off of which was given by the President of the Republic, Mr. Abdelmadjid Tebboune, on July 5, 2023, is 80%, the concrete work having been completed, while the work on the various networks will soon begin.





Source link

Leave a Reply

Your email address will not be published. Required fields are marked *

Please enable JavaScript in your browser to complete this form.
Address
Enable Notifications OK No thanks